South, Linden & Davis Road Closures

School is out and summer is in full swing for Jackson Center; and that means it is time for Construction.  Please see the Construction Schedule below for important dates and road closures:

May 25th - 302 South Main Street will be demolished, restricted traffic.

May 30th & 31st - The Davis Street railroad crossing will be closed so that the boring can be completed for the water main.

June 5th - June 9th - Davis Street will be closed from Main Street (St. Rt. 65) to Howard Street so that the Water main can be installed.

Once the Water Main is installed, the street will be patched and opened back up to traffic from the railroad tracks east to Howard Street.

Tom's Construction states that they will try to maintain the streets for the residents of Davis Street to their houses.

June 5th - August 11th - South Street, Linden Street (from South Street to the Safety Building (Firehouse), Davis Street from Main Street (St. Rt. 65) east to the railroad tracks will be closed to all traffic.  All traffic means:  no golf carts, all-terrain vehicles, motorcycles, bicycles etc.

During this time, all of the sidewalks, curb, gutter and pavement will be torn out.  The School is set for demolition during this time as well.

Parking for the Library will be in a marked area behind Subway.